A time has come to replace an old beam bridge over the same creek. We wanted an arched bridge, so here’s the blueprint, by Romas:

hroble, Mindaugas and ffwd have poured the concrete foundations over one weekend, with help from Tolikas and Vidas. Some items, including a mobile phone, were accidentally sacrificed over the process. Then a lot of people carried over the heavy glued timber beams that were bought from Jūrės medis.

We (hroble, pwf, ffwd, Elvinas and opit) fixed them into place with threaded rods at both ends, then covered them with small planks hroble and Karolina sanded and impregnated with linseed oil.

A bonus cat picture:

Railings will be added after the first casualty.